Third-party inspection has been completed for an ASTM A182 F22 flange order. The independent inspector reviewed traceability and material records, witnessed selected verification activities and confirmed dimensional, NDE, marking and packing requirements against the approved inspection and test plan.
Quick Answer: This F22 project completed purchaser-defined third-party inspection before release. Buyers should agree on the ITP hold and witness points, traceability, test extent, acceptance criteria and release documents before manufacturing begins.
Project snapshot
| Project status | Third-party inspection completed |
|---|---|
| Material | ASTM A182 F22 forged alloy steel |
| Flange type | Weld neck, slip-on and blind |
| Standard | ASME B16.5 |
| Pressure class | Class 300–900 |
| Size range | NPS 2–16 |
| Inspection | MTC review, PMI, hardness, UT, dimensions, marking and packing |
| Application | Petrochemical process piping |
Delivery highlights
What the independent inspector reviewed
The review began with the purchase order, approved drawings, material certificates and inspection and test plan. Heat numbers on the flanges were matched to records before selected PMI, hardness and NDE results were accepted. Calibration status and report identification were included in the document review.
Dimensional inspection covered the characteristics identified by flange type, including drilling, facing, thickness, hub or bore details and marking. The inspector also reviewed the visible condition of gasket faces and weld preparations.
From inspection release to packing
Third-party involvement does not transfer design responsibility or replace the manufacturer’s quality system. It provides independent evidence that the defined hold or witness points were completed. Any observations are resolved through the project procedure before release.
After acceptance, sealing faces were covered and the packing list was reconciled with the released quantities and identification. Inspection records were compiled into the final manufacturing record book as required.
Information needed for a comparable RFQ
A comparable inquiry should identify the exact material specification and grade, governing standard and edition, NPS, pressure class, flange type, facing, bore or matching pipe schedule, quantity and destination. For this project-news scope, the key reference points were ASTM A182 F22 forged alloy steel, Weld neck, slip-on and blind, Class 300–900 and NPS 2–16.
State the required EN 10204 certificate type, heat-number traceability, PMI extent, hardness limits, dimensional report, NDE method and acceptance standard, third-party witness points, packing method and required delivery date at quotation stage. Early definition allows manufacturing, inspection and document schedules to be reviewed together.
Production, inspection and packing photos
Images show the relevant SASA FLANGE production, quality-control and shipment stages used for this project-news report.



Related technical guides
ITP checkpoints for a comparable F22 flange order
The inspection scope changes with flange type and the approved purchase documents. Use these checkpoints to define what the purchaser or third party must review; they do not imply that every test is mandatory on every flange.
| Checkpoint | Evidence to define or review | Release question |
|---|---|---|
| Material and traceability | PO item, exact F22 class, heat number, MTC and physical marking | Can each supplied item be traced to its accepted material record? |
| Test plan and witness scope | Approved ITP revision, hold or witness designation, notice period and inspector sign-off | Were the agreed stages released before the next operation? |
| Verification and examination | Specified PMI, hardness and NDE method, coverage, calibration, acceptance basis and reports | Do reports identify the inspected item and disposition of any indication? |
| Dimensions by flange type | Applicable ASME B16.5 edition and approved drawing; facing, drilling, bore or hub as relevant | Does the measured configuration match the purchase description? |
| Final documentation and packing | Released quantity, inspection record index, marking and face protection | Can the receiver reconcile shipped items with the approved release file? |
For a mixed weld-neck, slip-on and blind-flange requirement, send the itemized list and approved drawings through the project RFQ. A single product example cannot represent all three types.
Frequently asked questions
Does third-party inspection replace the manufacturer’s inspection?
No. It independently witnesses or reviews defined activities; the manufacturer remains responsible for its quality controls and contractual compliance.
What is an ITP hold point?
A hold point is a stage that cannot proceed until the required party has reviewed or released it under the approved inspection and test plan.
Can the inspection scope be added after production?
Some reviews may be possible, but witness points and test extent should be agreed before manufacturing to avoid unavailable evidence or rework.